MEMORANDUM
To: Glenna Donnelly
Acting Deputy Commissioner for Disability and Income Security Programs
From: Assistant Inspector General for Audit
Subject: Assessment of the Electronic Disability Project (A-14-01-11044)
Thank you for the opportunity to participate on the Electronic Disability (eDib) Steering Committee. Audit involvement in systems development is a trend throughout the Government and private sectors, and we welcome the opportunity to be of assistance. This strategy will allow us to provide input throughout the development process instead of waiting until the project is complete and substantial funds have been expended. The Office of the Inspector General will not only participate in a consultative function, but will be active in identifying any fraud risk factors.
This memorandum is to provide you with two documents that we have developed while gathering information for the eDib project. First, we found 15 sites containing eDib information, which were not linked to the official eDib site on SSA’s Intranet (see Attachment A). Second, we created a detailed flowchart, which depicts the flow of information and related controls in Version 4.0 of the eDib (see Attachment B). We conducted our work in Baltimore, Maryland, and Wilmington, Delaware.
While searching the SSA Intranet for documentation relating to eDib, we noted that the Office of Systems Analysis maintained the primary eDib site, eDib Central Information Site. However, additional information was available from other SSA Intranet sites. On some of these sites, we found that the following offices had unique postings: Office of Systems Analysis had 21 postings, the Office of Telecommunications and Systems Operations had 21 postings, the Executive and Management Information System had 15 postings, and the unofficial site of Office of Systems Analysis had 10 postings.
It would be more efficient if the central site contained all the information, or at a minimum, provided links to the other sites containing eDib information. For this to succeed, the eDib Steering Committee needs to decide which component should control the central location to ensure all information is available. Attachment A lists the SSA Intranet sites containing eDib information and documents located on those sites as of May 14, 2001. As of October 5, 2001, we verified that the Intranet issues described above still existed.
During our search for information, we could not locate a detailed flowchart depicting the flow of information and related controls in Version 4.0 of eDib. This type of flowchart has been of great value to organizations. It simplifies the identification of internal controls and their interrelationships in a system and helps in assessing their adequacy.
Attachment B provides a flowchart, which we prepared with assistance from SSA’s Wilmington, Delaware staff, to show the eDib Version 4.0 process at work and the controls in that process. Our flowchart is based on the field office procedure followed to process a claim in the eDib "proof of concept" site of Wilmington, Delaware. We designed our flowchart to show what forms are accessed to complete most claims because the key system controls are inherent in this process. Upon your request, we are ready to work with SSA staff to update this flowchart as needed.
Based on the information we found, we suggest the eDib Steering Committee:
We prepared these suggestions to help facilitate the eDib systems development process. There is no expectation for the Agency to formally respond to these suggestions. We look forward to participating in the eDib Steering Committee. If you have any questions or comments, please call me or have your staff contact Kitt Winter, Director, Systems Audit Division at (410) 965-9702. Members of the eDib Steering Committee may contact Ms. Winter directly or Al Darago at (410) 965-9710.
Steven L. Schaeffer
Site Source |
Item Date |
Item Title |
OSA eDib Site |
Background Information on eDib |
|
OSA eDib Site |
2000-08-03 |
Management Plan for the development of the Agency's Electronic Disability System eDib |
OSA eDib Site |
eDib Project Scope Agreements Version 1 |
|
OSA eDib Site |
eDib Project Scope Agreements Version 2 |
|
OSA eDib Site |
1999-12-17 |
eDib Project Scope Agreements Version 3, Version 1.6 |
OSPI |
1999-12-09 |
eDib Project Scope Agreements Version 3, Version 1.5 |
OSA eDib Site |
2000-03-08 |
eDib Project Scope Agreements Version 4 |
OSA eDib Site |
|
eDib Project Scope Agreements Version 4.1, version 1.4 |
OSPI |
eDib Project Scope Agreements Version 4.1, version 1.4 |
|
OSA eDib Site |
2000-12-01 |
FAQs |
OSA eDib Site |
2000-05-02 |
Contacts for hardware, configuration or software problems |
OSA eDib Site |
2001-02-01 |
Version 4 Problems and their status |
OSA eDib Site |
2000-06-08 |
Electronic Folder - Statement of Work |
OSA eDib Site |
Electronic Folder - Effort to Contract with Levy and Versa to Build Generic Interfaces to SSA’s Electronic Disability Folder |
OSA eDib Site |
2000-12-07 |
Electronic Folder - Electronic Disability (eDib) Strategy Paper |
OSA eDib Site |
2000-05-03 |
Electronic Folder - Business Process Description for eDib Version 3 |
OSA eDib Site |
Electronic Folder- eDib field office to DDS Claim Transfer graphic |
|
OSA eDib Site |
Electronic Folder - Plan to Identify eDib Pilot Sites |
|
OSA eDib Site |
2000-05-01 |
Electronic Folder - STRAWMAN PAPERLESS BUSINESS PROCESS DESCRIPTION |
OSA eDib Site |
2000-11-01 |
New York Paperless Pilot System - KEY INITIATIVE CONCEPT PAPER |
OSA eDib Site |
2000-11-15 |
New York Paperless
Pilot System - |
OSA eDib Site |
Regional Contacts |
|
OSA eDib Site |
SSA Web: eDib Central Site |
|
EMIS |
2000-02-29 |
Key Initiative Plan and Schedule |
OSA |
5-year plan - eDib |
|
OTSO |
Oracle Instance Report |
|
EMIS |
SSA FY 2002 Annual
Performance Plan – p78 |
|
OTSO |
2000-03-21 |
Wang/Levy 3/22/00
– Summary of Federal Day at Spring SASUS held in Tuscon AZ March 21, 2000 |
EMIS |
2000-10-06 |
FY2002 Working Documents – edib entry points to key initiative plan and schedule as of 02/29/2000 |
EMIS |
2001-01-? |
The Role of the Office of Systems |
OSDD |
OSDD Projects |
|
STECS |
Data Link - The Lab Corner |
|
OTSO |
2001-02-15 |
Distributed Data Architecture Team list of UNIX servers as of 2/15/01 |
OSDD |
DSEL Projects has created a simulated production Wide Area Network (WAN) environment for client-server application testing and validation. |
|
OSA |
SEC.xls Security Support data for edib versions 4.0 4.1, 4.2, 4.3 and 5.0 |
|
OTSO |
Non prod oracle servers.xls |
|
EMIS |
2002 Program for Objective Summary Report DI/SSI |
|
OSA |
Hw.xls – item 83 is edib support project |
|
OSA |
CTW Chart 9-00.xls |
|
OSA |
Division of Claims and Controls listing employees assigned to EF and edib-MIDAS interface |
|
|
October 2000 LSTT Application Assignments |
|
IWSLAN Software Testing Team |
||
OTSO |
LAN Software Testing Team Home Page |
|
OSPI |
CTW Function Point Report for edib release 4.2 |
|
EMIS |
Key Initiatives as of January 2001 |
|
OIM |
OIM MIB Disability Systems Branch |
|
EMIS |
200-10-06 |
FY 2003 Working Documents (edib file password protected) |
EMIS |
2000-12-01 |
Quarterly Management Meeting |
EMIS |
2001-02-08 |
Matrix.xls - List of FY 2002 programs and how they meet certain subsets of SSA’s objectives such as Responsive Programs, World Class Service, Program Integrity, Valued Employees and Public Understanding |
OTSO |
2000-02-29 |
Austin III Conference - OTSO presenters |
OTSO |
2000-08-30 |
Fall SASUS Notes |
OSA |
MI.xls – 5 year plans - edib mi version 4 is item 11 |
|
Appendix 3 - Description
of Key Initiatives |
||
EMIS |
2001-02-02 |
eDib section on page
11 |
Appendix 5 – Key Initiative
Table of Contents |
||
DCS |
Systems Partnership Council - Draft Minutes |
|
EMIS |
2001-05-08 |
List of FY 2002 programs and how they meet certain subsets of SSA’s objectives such as Responsive Programs, World Class Service, Program Integrity, Valued Employees and Public Understanding |
OTSO |
1999-10-19 |
Laptops IMB ThinkPad
600E Notebook – Power Point Presentation Cost $67.250 Million
|
STECS |
SEF Configuration
Page 1 |
|
EMIS |
2001-02-15 |
The Role of Key Initiative
Leads and Teams |
OSDD |
Distributed Software
Engineering Library |
|
EMIS |
Key Initiative: Return
to Work |
|
EMIS |
2000-02-08 |
Quarterly Workload
Meeting |
OSA |
2001-02-12 |
Functional Directory of OSA. eDib on pages 6 and 35 |
OSA |
OSA Division of Requirements Support and Security – Lists contacts in Control Audit and Security Branch and subsets CATF, Audit and Integrity Review Team, and Security and Internal Control Team. The Network/Exchange/ Office Automation Team has responsibility for determining imaging H/W and S/W requirements for edib |
|
STECS |
2000-09-01 |
Identify Security
Requirements Early |
OTSO |
2000-10-19 |
Forecast.xls – Description
and status of initiatives |
OTSO |
Onlineappl.old |
|
OTSO |
Ccbdly.rtf |
OTSO |
Applications in Production |
|
OSA |
OSA Division of SSI Systems |
|
OTSO |
Ccbdly.old |
|
SYSCONF |
2001/06/06 |
Systems Conference Agenda 06/06/2001 |
TRAINING |
Index of Online Courses (select E and then scroll down for 12 edib courses) |
|
OTSO |
Who wants to be an eDib Expert presentation given at the 2001 Spring SASUS conference |
|
OSA |
OSA Home Page with eDib selection option |
|
SSAWIN2000 |
DIET paperless FO Test for Windows 2000 |
|
SYSCONF |
A list of the presentations to be given at this year's conference. |
|
OTSO |
SASUS 2001 list of
Presentations |
|
OTSO |
Applications Monitored
by SmartWatch |
OTSO |
2001-05-04 |
System Information on status of UNIX host machines using CA management software Unicenter TNG and firewall software tool, eTrust |
EMIS |
2001-04-18 |
Implement activities necessary to have the software and infrastructure in place for paperless processing of disability claims - This goal will have been met if we develop, test, validate and implement release 3.8 of MCS. This goal will have been met when we develop, test, validate, implement and evaluate Version 4 of eDib |
OTSO |
2001-05-01 |
NS-Elite Replacement Offsite Power Point Presentation Screen 5 of 7 shows that edib will be affected |
OTSO |
2001-05-01 |
Client Server Configuration
Meeting Minutes 04/04/01 – Item 2 gives edib status |
OTSO |
2001-03-20 |
OTSO Presentation at Spring SASUS on Technology Initiatives. SSAnet Modernization, Frame Relay, Virtual Private Network, AS400 support for DDS |
2001-04-01 |
Office of Public Service and Operations Support (OPSOS). OPSOS is responsible for the operational delivery of public service and the overall effectiveness and efficiency of DCO components. We conduct studies, analyses and implementation planning on a myriad of issues related to the RSDI, SSI and HI programs, and provide leadership on customer service delivery, budget, management information and administration issues. The Division of Program Policy and Operations works with the Regions and central office components to develop and implement new legislation, new policies, and to develop strategies to improve current existing policies and service delivery. The Disability Analysis Branch is responsible for issues related to the disability program. In DAB, the person monitoring edib and HIPAA is Gillian Crane. |
|
DDS |
2000-11-01 |
DDS Mini Forum – Florida. Slide show on frame relay |
DCO |
OAS Highlights |
|
philanet |
eDib Delaware pilot web site |